Sydenhams (Timber Engineering) Ltd v CHG Holdings
Ltd
[2007]
EWHC 1129 (TCC)
Nature of case
Claim by a timber frame supplier (C) against a hotel developer
(D) for payment. D claimed that C was a sub-contractor and
had no direct claim for payment after the insolvency of the main
contractor. HHJ Coulson held that C had entered into direct
negotiations and contractual arrangements with D both before and
after the insolvency of the main contractor, which entitled C to
payment from D.