The JCT 2005 Standard Forms of Construction
Contract
12 January 2006
Speakers Philip Boulding QC
Introduction
1. The JCT’s introduction of the 2005 suite of standard
form construction contracts is certainly more than just a
“facelifting” exercise. Not only have the 2005 forms been redrafted
using less legalistic language and sorted into a more user-friendly
format, important developments have also been incorporated,
triggered by changes in both the industry and the law.
2. Space and time prevent an exhaustive analysis of all such
developments. Instead, the focus of this talk will be on four key
areas in which the most striking changes appear to have been made,
namely:
(1) The layout and structure of the 2005 forms;
(2) Contractor’s design responsibilities;
(3) Third Party Rights;
(4) Dispute resolution.
(I) Layout and Structure of the 2005 forms
3. The drafting of the 2005 forms has been heavily
influenced by a search for uniformity and modernisation (probably
influenced by the fact that they are newly published by Sweet &
Maxwell). This has manifested itself in several different
ways.
Section-Headed Approach
4. The documents published so far adopt a “section-headed”
approach rather than a “clause-by-clause” structure, splitting each
contract into parts with titles such as “Carrying Out the Works”,
“Control of the Works” etc.
5. To a familiar user of the 1998 forms, such a re-jigging
certainly appears a little unfamiliar. The sectional approach has
had the effect of rearranging the conditions in such forms. (It is
important to be aware that, although there have been some
significant changes to substance, for the most part the new forms
do reflect the provisions of the old (although those provisions may
have moved around – so you will need to cross-check!)).
6. The net result is an undoubtedly more “user-friendly”
contract designed to be more accessible to contracting parties and
construction professionals alike.
Project-Specific Approach
7. Perhaps in an attempt to encourage contracting parties to
properly fill in details of the works to which the contract
relates, “project-specific” information, traditionally located in
the Appendix to the conditions, has been shifted to the front of
the Contract in what is generally known as the “Contract
Particulars”.
8. The Contract Particulars also include, for the first
time, the identity of parties to whom third party rights are to be
given and factors regulating liability under the contract such as
net contribution clauses for subcontractors. This is an important
inclusion and is discussed in more detail below.
Integration of
Supplements
9. Another welcome development is
the integration of some supplements into the main text of the 2005
Contracts, obviating the need to read two documents together or, in
the case of hard copies, to make numerous amendments to
clauses.
10. For example, under the Standard Building Contract 2005
(“SBC 2005”), sectional completion is dealt with by express
contractual provisions (in particular, the Articles of Agreement,
the Contract Particulars, the Definitions under clause 1 and the
Conditions) rather than by the addition and incorporation of a
supplement.
Greater use of Schedules
11. On the other hand, curtailments to the body of the
standard form text have been made by cross-referring back to the
Contract Particulars. For example, under the 1998 standard form
contract there were lengthy options for the insurance of the works
under clauses 22A, 22B or 22C, meaning that once one of these has
been selected, the other two clauses are rendered superfluous. The
result was unwieldy and potentially confusing.
12. Clause 6.7 of SBC 2005 now simply provides:
“Insurance Options A, B and C are set out in schedule 3. The
Insurance Option that applies to this Contract is that stated in
the Contract Particulars”
Publication of Guides
13. The
JCT has produced “guides” to assist the user in finding the
equivalent provisions in the older standard form contracts in the
new editions.
14. Whether such guides will be used by contracting parties
as a reference tool (which is presumably what they are intended to
be) or as a resource for bespoke amendments remains to be seen…
(II) Contractor’s Design Responsibilities
15. The 2005 reformatting of the JCT contracts has seen two
notable additions to the range, namely the Minor Works Building
Contract with Contractor’s Design (“MWD 2005”) and Intermediate
Works Building Contract with Contractor’s Design (“ICD 2005”),
specifically tailored for the smaller end of the market where the
contractor provides some design input subject to supervision from
the architect or contract administrator.
16. Neither contract is intended to be a substitute for a
design and build contract; indeed, both appear only to be suitable
in circumstances where the parties intend that the contractor is to
be responsible for a discrete element of the design.
17. Perhaps in order to emphasise this point, both
contracts oblige the employer (i) to supply detailed requirements
for the intended “contractor’s design portion”, (ii) to examine the
contractor’s proposals in respect of such requirements and (iii) to
satisfy himself that those proposals are adequate (see Seventh
Recital).
18. It is of course open to an employer to delete or amend
such provisions in an attempt to impose a more onerous design
responsibility upon a contractor than was intended by JCT
draftsmen. This may well be an area where disputes occur.
19. More interestingly from the lawyer’s point of view, the
contractor’s design obligation differs between the two contracts.
Under ICD 2005, the standard of care in relation to the design of
the particular portion is that of a professional designer.
(1) . Conversely, under MWD 2005 the
standard is that of reasonable skill, care and
diligence. (2). The question which
presumably will be left for the courts to decide is whether the
reasonable skill and care to be expected of a contractor carrying
out design work is different to the skill and care to be expected
of a professional designer.
Contractor’s obligation to “complete” the
design
20. By including a clause within SBC
2005, DB 2005, IDP 2005 and MWD 2005 which expressly provides that
a contractor is not responsible for checking the adequacy of any
design contained within the employer’s requirements, the JCT
appears to have kicked the principle laid down by the decision in
Cooperative Insurance Society v Henry Boot
Scotland Limited (2003) CLJ 19 109 squarely into touch.
21. In Boot, HHJ Seymour QC held that a contractor charged
with “completion” of design work was under a duty of care to
examine an employer’s pre-existing design and to satisfy himself
that the same was such that would produce a completed design
capable of being constructed.
22. However, this is not to say that a contractor has no
responsibility whatsoever in relation to the design:
(1) under SBC 2005, DB 2005 and ICD 2005 (though not MWD
2005), a contractor is obliged to notify any inadequacies in the
employer’s requirements upon becoming aware of the same, and then
to seek reimbursement for related costs by way of a variation;
(2) Further (save under MWD 2005), it is incumbent on the
contractor to ensure that the employer’s design complies with any
statutory requirements (except in the case of DB 2005 where the
employer’s requirements state that they are so compliant).
Design Review
Procedure
23. Both DB 2005 and SBC 2005
(3) contain a “design review procedure”
whereby the contractor is required to submit all design documents
that it prepares for review. Following such a review, design
documents are graded as follows:
(1) “A” – contractor to proceed with the works in
accordance with the design document. To prevent any undue delay, a
design is deemed to have been marked “A” in the event that it is
not returned within 14 days of submission;
(2) “B” – contractor proceed with the works in accordance
with architect/employer comments. Design must also be amended to
take on board such comments;
(3) “C” – contractor to resubmit design document
incorporating comments made. No works to be carried
out.
24. A contractor is only entitled to be paid in respect of
such work where it has been executed in accordance with designs
marked A or B.
25. It remains to be seen whether an employer may seek to
cross the line between making comments on designs which are for the
purposes of gaining confidence that the contractor is having proper
regard to the contractual requirements and making comments which,
in effect, attempt to vary the design requirements via the back
door. To protect against this, a contractor is required to raise
any challenges to comments which appear to introduce a variation
within 7 days of the comment being made. Absent this, such comments
will be deemed not to constitute a variation.
(III) Third Party Rights
26. Despite a clear market demand for collateral
warranties, especially following the infamous decision of the House
of Lords in Murphy v Brentwood, the JCT has consistently refused to
incorporate provisions for a contractual warranty between main
contractor and third parties (principally purchasers, tenants and
funders). Inevitably, such a provision led to a proliferation of
bespoke forms of collateral warranties.
27. The granting of third party rights has already been
included in the 2003 Major Project Form (“MPF”) (although this did
not and does not extend to the provision of warranties).
28. Perhaps encouraged by the MPF, or alarmed by the number
of bespoke warranties in existence, SBC 2005, DB 2005 and IC/ICD
2005 now include provisions for main contractor and subcontractor
collateral warranties in favour of purchasers, tenants and
funders.
29. However, it should be noted that the nature of such
provisions varies markedly across the 2005 suite of contracts. For
example, the MW/MWD05 contains no such clauses, whereas the SBC 05
makes provision for collateral warranties, sub-contractor
collateral warranties and the granting of third party rights.
30. Should such provisions exist, it is critical that the
Contract Particulars in relation to warranties or third party
rights are carefully filled in. In addition to identifying the
beneficiaries, the parties also need to identify the part of the
works to be purchased or let and whether or not a warranty or third
party rights are to be granted (if a choice is available).
31. Specific details requiring attention include whether or
not a contractor is to be liable for non-repair losses incurred by
the beneficiary and any “cap” to be applied to the net contribution
clause of the warranty. Should no purchasers, tenants or
funders be identified by name, class or description, then an
employer will not be able to subsequently ask for warranties or
third party rights in relation to the same.
32. A notice identifying (i) the relevant purchaser, tenant
or funder and (ii) his particular interest in the works must be
served by actual, special or recorded delivery upon the contractor,
following which the contractor has fourteen days to enter into the
relevant form of warranty. Third party rights vest in the
appropriate beneficiaries upon the contractor’s receipt of a notice
from the employer.
33. Should sub-contractor remedies be required (as provided
for under IC/ICD 05, SBC 05 and DB 05) then it is incumbent upon
the contractor to “comply with the requirements set out in the
Contract Documents as to obtaining such warranties”. It is up to
the parties to decide whether such an obligation is absolute or
restricted to using the contractor’s “best endeavours” or
“reasonable endeavours”.
34. The 2005 suite anticipates that standard form
warranties (such as the JCT CWa/P&T (for purchasers and
tenants) or the JCT CWa/F (for funders)) will be adopted by the
parties, but the contracts provide that the agreed forms are
subject to bespoke amendments.
(IV) Dispute Resolution
35. For the lawyer and construction professional alike,
perhaps the most significant practical development implemented by
the 2005 forms has been the apparent sea change to the familiar JCT
dispute resolution procedure.
36. Whilst the draftsmen have shied away from a “uniform”
procedure, applicable across the entire 2005 suite of, it is fair
to say that the new forms see arbitration as being on the wane.
SBC 2005
Adjudication
37. The JCT Adjudication rules
have been scrapped in favour of the Scheme for Construction
Contracts.
38. One significant consequence of this is that it would
seem that no more than one dispute at a time can be referred. It
had previously been decided that under the JCT adjudication
provisions (but not the Scheme) multiple disputes could be referred
in one adjudication – R Durtnell & Sons
v Kaduna Ltd [2003] BLR 225.
Arbitration
39. Arbitration still exists but is no longer the default
position; for it to apply, an express entry must be made in the
Contract Particulars against Article 8.
40. Even though the draftsmen did not go as far as removing
the provision for arbitration entirely, such as in the case of the
MPF, this development remains a particularly interesting one,
especially in the light of the recent shake-up of the TCC.
MW 2005/IC2005
41. The dispute
resolution procedure under these two forms is broadly the same as
the SBC 2005. However, given that both forms may well be used by
parties who fall within the definition of “residential occupiers”
for the purposes of s.106 Housing Grants, Construction and
Regeneration Act 1996, the accompanying guides to each contract
contain a “health warning”:
IC 2005
107. Care needs to be taken where an Intermediate Building
Contract is used for a contract with a residential occupier within
the meaning of section 106 HGRA 1996…
108. Since Part II of that Act does not apply to contracts
with residential occupiers, as defined, the Employer’s Architect or
contract administrator may be under a duty to advise his or her
client(s) accordingly, in particular with regard to adjudication
and as to whether or not to disapply Article 7 and clause 9.2.
MW 2005
6. The Contract complies with the requirements of the Housing
Grants, Construction and Regeneration Act 1996 in providing for
adjudication and certain payment provisions; however, not all
building contracts are subject to this Act. For example, a contract
with a residential occupier within the meaning of section 106 of
the Act is excluded and therefore it does not need to contain
adjudication provisions, but a residential occupier in entering
into a Minor Works Building Contract will be accepting adjudication
as a means of resolving disputes.
V. Conclusions
42. In general terms, the changes implemented by the 2005
suite of JCT contracts are to be welcomed and evidences the fact
that constructive criticism from commentators is not necessarily
ignored! (4)
43. However, as with all contracts, it will be open to the
parties to amend, add or omit certain clauses – especially those
which appear unfamiliar. For example, issues in relation to the
existence and extent of a contractor’s design responsibility may be
an area which proves to be particularly fruitful for those in the
legal profession.
For further information…(!)
44. See the forthcoming publication “Keating on the JCT
Contracts” which will:
• Be published by Sweet & Maxwell (and written by
members of Keating Chambers)
• Provide clause by clause commentary on (eventually) all of
the new suite
• Be in looseleaf and updated format
• Contain extensive cross-referencing to Keating on Building
Contracts (new edition also out shortly!)
(1) clause 2.34.1
(2) clause 2.1.1
(3) although only if the Contractor's Design Portion in the Seventh
Recital is appliable
(4) by way of example, we would like to think that the removal of
all provisions in relation to nominated subcontractors is in no
small part due to the criticism leveied towards the same in Keating
on Building Contracts!
The articles and papers published by Keating Chambers are for
the purpose of raising general awareness of issues and stimulating
discussion. The contents must not be relied upon or applied in any
given situation. There is no substitute for taking appropriate
professional advice.
Back to Seminars