Adjudication Round-up: key decisions and developments
2004-2006
5 April 2006
Speakers Abdul Jinadu
Introduction
1. This paper covers the following issues:
I: Adjudication Round-up: key decisions and
developments 2004-2006.
(i) Areas of challenge of adjudication decisions:
jurisdiction.
(ii) Areas of challenge of adjudication decisions: natural
justice.
II: Focus on special topics in adjudication.
(i) Proactive Adjudicators – the extent to which adjudicators
can take the initiative in procedure.
(ii) Confidentiality and disclosure in adjudication
proceedings.
I. Challenge of Adjudicator's Decisions -
Jurisdiction
2. There have been recent cases in relation to two aspects
of the jurisdiction of adjudicators:
(a) The existence of a dispute
(b) Whether a contract is in writing within the meaning of the
Housing Grants etc. Act 1996
The Existence of a “Dispute”
3. In AMEC Civil Engineering Ltd v
Secretary of State for Transport [2004] EWHC 2339 (TCC),
Jackson J. analysed the authorities on the existence of a dispute
and summarised the legal position as follows:
1. The word "dispute" which occurs in many arbitration
clauses and also in section 108 of the Housing Grants Act should be
given its normal meaning. It does not have some special or unusual
meaning conferred upon it by lawyers.
2. Despite the simple meaning of the word "dispute", there
has been much litigation over the years as to whether or not
disputes existed in particular situations. This litigation has not
generated any hard-edged legal rules as to what is or is not a
dispute. However, the accumulating judicial decisions have produced
helpful guidance.
3. The mere fact that one party (whom I shall call "the
claimant") notifies the other party (whom I shall call "the
respondent") of a claim does not automatically and immediately give
rise to a dispute. It is clear, both as a matter of language and
from judicial decisions, that a dispute does not arise unless and
until it emerges that the claim is not admitted.
4. The circumstances from which it may emerge that a claim
is not admitted are Protean. For example, there may be an express
rejection of the claim. There may be discussions between the
parties from which objectively it is to be inferred that the claim
is not admitted. The respondent may prevaricate, thus giving rise
to the inference that he does not admit the claim. The respondent
may simply remain silent for a period of time, thus giving rise to
the same inference.
5. The period of time for which a respondent may remain
silent before a dispute is to be inferred depends heavily upon the
facts of the case and the contractual structure. Where the gist of
the claim is well known and it is obviously controversial, a very
short period of silence may suffice to give rise to this inference.
Where the claim is notified to some agent of the respondent who has
a legal duty to consider the claim independently and then give a
considered response, a longer period of time may be required before
it can be inferred that mere silence gives rise to a
dispute.
6. If the claimant imposes upon the respondent a deadline
for responding to the claim, that deadline does not have the
automatic effect of curtailing what would otherwise be a reasonable
time for responding. On the other hand, a stated deadline and the
reasons for its imposition may be relevant factors when the court
comes to consider what is a reasonable time for
responding.
7. If the claim as presented by the claimant is so nebulous
and ill-defined that the respondent cannot sensibly respond to it,
neither silence by the respondent nor even an express non-admission
is likely to give rise to a dispute for the purposes of arbitration
or adjudication.”
4. This summary of the law has been supported on two
occasions by the Court of Appeal (see AMEC
Civil Engineering Ltd v Secretary of State for Transport
[2005] EWCA Civ 291 and Collins
(Contractors) Ltd v Baltic Quay Management (1994) Limited
(2004) EWCA Civ 1757).
5. The wording of the first paragraph of Jackson J.’s
summary also appears to confirm that the meaning of dispute is the
same in relation to both adjudication and arbitration
proceedings.
6. The Court of Appeal in Collins
(Contractors) Ltd v Baltic Quay Management (1994) Limited
(supra) added a further gloss to the question of when a dispute
will be found to exist by stating a preference for the view that
negotiations or discussions are generally consistent with a dispute
being in existence as opposed to the alternative view that no
dispute crystallises until negotiations or discussions have
concluded without success.
Contracts in writing
7. In Trustees of Stratfield Saye
Estate v AHL Construction Ltd [2004] EWHC 3286, Jackson J.
clarified the extent to which a contract must be in writing before
falling within the mandatory adjudication provisions of the Housing
Grants, Construction and Regeneration Act 1996 (“HGCRA”).
8. He considered the Court of Appeal decision in
RJT Consulting Engineers Ltd v DM
Engineering Ltd [2002] EWCA Civ 270 and held that its ratio
was that all the express terms of the contract had to be in writing
for the HGCRA to apply. However, the contract need not be
found in a formal document and on the facts the contract was
adequately evidenced in writing by letters, drawings and meeting
minutes.
II. Challenge of Adjudicator's Decisions – Natural
Justice
General
9. In AMEC Capital Projects Limited
v Whitefriars City Estates Limited [2004] EWCA Civ 1418, the
common law rules of natural justice were described as being two
fold:
(a) The right to proper notice and an effective opportunity to
make representations before a decision is made
(b) The right to an unbiased tribunal
10. In Carillion Construction Ltd v
Devonport Royal Dockyard Ltd [2005] EWHC 778 (TCC), Jackson
J. summarised the authorities on the requirements of natural
justice as follows:
1. If an adjudicator declines to consider evidence which, on
his analysis of the facts or the law, is irrelevant, that is
neither (a) a breach of the rules of natural justice nor (b) a
failure to consider relevant material which undermines his decision
on Wednesbury grounds or for breach of paragraph 17 of the Scheme.
If the adjudicator's analysis of the facts or the law was
erroneous, it may follow that he ought to have considered the
evidence in question. The possibility of such error is inherent in
the adjudication system. It is not a ground for refusing to enforce
the adjudicator's decision…
…
3. It is often not practicable for an adjudicator to put to
the parties his provisional conclusions for comment. Very often
those provisional conclusions will represent some intermediate
position, for which neither party was contending. It will only be
in an exceptional case such as Balfour Beatty v London Borough of
Lambeth that an adjudicator's failure to put his provisional
conclusions to the parties will constitute such a serious breach of
the rules of natural justice that the Court will decline to enforce
his decision.
…
5. If an adjudicator is requested to give reasons pursuant
to paragraph 22 of the Scheme, in my view a brief statement of
those reasons will suffice. The reasons should be sufficient to
show that the adjudicator has dealt with the issues remitted to him
and what his conclusions are on those issues. It will only be in
extreme circumstances… that the court will decline to enforce an
otherwise valid adjudicator's decision because of the inadequacy of
the reasons given. The complainant would need to show that the
reasons were absent or unintelligible and that, as a result, he had
suffered substantial prejudice.
11. This summary indicates that the Courts will be
reluctant to allow a party to resist enforcement on the basis of a
breach of the principles of natural justice.
Right to proper notice
12. In Ardmore Construction Limited v
Taylor Woodrow Construction Limited [2006] CSOH 3 an
adjudicator’s decision was set aside as it was based upon an
argument which the Outer House concluded had not been run at the
adjudication hearing. The defenders had not, therefore,
received proper notice and opportunity to respond.
13. The case is noteworthy because the Outer House, while
acknowledging the strict approach to arguments of natural justice
advocated in Carillion v Devonport (supra), appeared to retreat
somewhat from Jackson J.’s position, stating:
“if [adjudicators] behave, in reaching their decisions, in a
manner which, on an objective basis, involves a disregard of fair
play, the consequence of which appears to have had a substantial
and material effect on the adjudicator’s decision, then the Court
should be prepared to intervene.”
Bias
14. In A&S Enterprises Limited
v Kema Holdings Limited [2005] BLR 76 an adjudicator drew
adverse inferences from the non-participation of a particular
witness at a meeting. HHJ Seymour QC found there had been a
breach of natural justice both because the adjudicator had failed
to make clear in advance the importance he was attributing to the
non-participation of the witness and because his actions indicated
a real possibility of bias.
15. Both these findings turn to some extent upon the facts
of the case. In particular, the finding of bias stems from
the adjudicator’s statement that he had viewed the Responding
Party’s submissions and arguments in the light of the unexplained
non-attendance of the witness at the meeting. HHJ Seymour QC
considered this to mean that the non-attendance influenced legal
findings as well as factual findings and equated this with
bias.
III. Pro-active Adjudication
16. Section 108(2) of the HGCRA states:
The contract shall…
…
(f) enable the adjudicator to take the initiative in
ascertaining the facts and the law
17. This section therefore requires that adjudicators be
granted broad ranging inquisitorial powers similar to those
provided to arbitrators under s.34(2)(g) of the Arbitration Act
1996.
18. In principle, there do not appear to be any limits on
the powers of adjudicators to take the initiative in determining
the procedure of hearings other than the general limits relating to
natural justice.
19. For adjudications governed by the Scheme for
Construction Contracts, Paragraph 13 provides for certain specific
powers:
The adjudicator may take the initiative in ascertaining the
facts and the law necessary to determine the dispute, and shall
decide on the procedure to be followed in the adjudication.
In particular he may –
(a) request any party to the contract to supply him with such
documents as he may reasonably require, including, if he so
directs, any written statement from any party to the contract
supporting or supplementing the referral notice and any other
documents given under paragraphs 7(2).
(b) decide the language or languages to be used in the
adjudication and whether a translation of any document is to be
provided and if so by whom
(c) meet and question any of the parties to the contract and
their representatives
(d) subject to obtaining any necessary consent from a third
party or parties, make such site visits and inspections as he
considers appropriate, whether accompanied by the parties or
not,
(e) subject to obtaining any necessary consent from a third
party or parties carry out any tests or experiments,
(f) obtain and consider such representations and submissions
as he requires and, provided he has notified the parties of his
intention, appoint experts, assessors or legal advisors
(g) give directions as to the timetable for the adjudication,
any deadlines, or limits as to the length of written documents or
oral representations to be complied with, and
(h) issue other directions relating to the conduct of the
adjudication
20. These provisions give the adjudicator quite broad
discretion as to the procedure to be adopted. Further, the
wording of the paragraph suggests that these are “particular”
instances of the adjudicator’s powers and not an exhaustive
list.
21. One key procedural limitation can be found in Paragraph
17:
The adjudicator shall consider any relevant information
submitted to him by any of the parties to the dispute and shall
make available to them any information to be taken into account in
reaching his decision.
22. For non-Scheme adjudications, the powers of the
adjudicator will often be less clear. However, in the absence
of express limitations, the adjudicator will be constrained
primarily by natural justice. Although the Scheme will not
apply directly in such instances, Paragraphs 13 and 17 appear to
give a good indication of the extent to which an adjudicator can be
pro-active without breaching any principles of natural justice.
Independent Advice
23. One common manner in which adjudicators behave in a
pro-active manner is by obtaining advice and assistance
independently from the parties. This particularly happens
where the adjudicator is part of a large organisation which is
capable of replicating and independently confirming analyses
carried out by one or both parties.
24. In principle, there seems nothing objectionable about
this course of action, at least where the parties agree to it (see
Try Construction Ltd v Eton Town House
Group [2003] EWHC 60 (TCC)).
25. In such circumstances, the key limitation is the
principle of natural justice (also found in paragraph 17 of the
Scheme) which requires that the adjudicator provide the parties
with any findings obtained so that they can comment upon and
challenge them.
26. For example, in BAL (1996) Ltd
v Taylor Woodrow Construction (2004) (Lawtel) even though
the parties agreed that the adjudicator could obtain legal advice
from third party solicitors and Counsel the adjudicator was held to
have breached the principles of natural justice by failing to
disclose in the contents of the advice to the parties in advance of
his decision.
27. The position where the parties do not consent to the
adjudicators proposed use of independent advice is less
clear. The better view is probably that, as with other
procedural issues, the adjudicator has a general power to seek such
advice and is solely limited by the principles of natural justice
and the rules governing the arbitration.
28. In Balfour Beatty Construction
v London Borough of Lambeth [2002] EWHC 597 (TCC) a further
argument was raised that the adjudicator’s use of assistants
rendered the determination unenforceable because it was contrary to
the JCT rules governing the adjudication. HHJ Lloyd QC
considered that in order to resist enforcement on this basis, it
was necessary not only to show a breach of contract by the
adjudicator, but also material prejudice or substantial injustice
flowing from the breach. If this obiter statement correctly
reflects the law, arguments as to breach of contract and/or
adjudication rules appear to add little or nothing to the basic
requirements of natural justice.
Admission of late evidence and issues
29. Paragraph 17 (supra) of the Scheme requires the
adjudicator to consider all relevant information submitted to him
by the parties to the dispute. In non-Scheme adjudications,
it is likely that the principles of natural justice would require a
similar result.
30. However, where evidence is admitted late, the
adjudicator must sometimes be pro-active in excluding it on the
basis that it would be contrary to the principles of natural
justice to allow its admission.
31. An example of this can be found in London & Amsterdam Properties v Waterman
Partnership [2003] EWHC 3059 (TCC) where the claimant sought
to rely on late material brought forward only after the defendant’s
response. Although the respondent had a week to reply to this
new evidence, it was in the circumstances an inadequate amount of
time and the Court regarded the new material as an evidential
ambush the admission of which was contrary to the principles of
natural justice.
32. The same principle applies to the introduction of new
issues. In McAlpine v Transco
[2004] EWHC 2030 (TCC) the permitted McAlpine to introduce new
issues into the adjudication which had not been included in the
Notice of Adjudication or Referral Notice.
IV. Confidentiality and Disclosure
33. Many sets of adjudication rules provide specifically
for confidentiality:
(a) Paragraph 18 of the Scheme provides that:
The adjudicator and any party to the dispute shall not
disclose to any other person any information or document provided
to him in connection with the adjudication which the party
supplying it has indicated is to be treated as confidential, except
to the extent that it is necessary for the purposes of, or in
connection with, the adjudication.
(b) Paragraph 30 of the TeCSA adjudication rules
provides:
The Adjudication and all matters arising in the course
thereof are and will be kept confidential by the Parties except
insofar as necessary to implement or enforce any decision of the
Adjudicator or as may be required for the purpose of any subsequent
proceedings.
(c) Paragraph 19.4 of the TECBAR adjudication rules
provides:
Unless otherwise agreed, the Decision and the documents and
other information and materials prepared for use in the
adjudication, and any documents predating the adjudication produced
or exchanged between the parties but relating to the matters in
dispute in the adjudication, shall remain confidential to the
parties, and shall not be used for any purpose other than the
adjudication, except that nothing herein shall (a) bar their use by
any party in any connected arbitration, litigation or other dispute
resolution process or (b) bar their production by any party to any
person or body that has a financial or commercial interest in the
contract itself and/or is (or is contemplating) providing
facilities to one or other of the
parties.
34. As these clauses demonstrate, adjudication rules which
provide for confidentiality generally provide that the whole
hearing is confidential with a minor exception for the purposes of
enforcement proceedings.
35. The position where the adjudication is conducted under
rules which do not provide for confidentiality is unclear. In
such situations, the party resisting disclosure would perhaps be
best advised to refuse disclosure unless an undertaking as to
confidentiality is received. This would seem to be a
reasonable request and if the undertaking were not forthcoming it
could be considered contrary to the principles of natural justice
to draw any adverse inferences from the refusal to provide the
confidential documents.
Disclosure
36. In CIB Properties Limited v
Birse Construction [2004] EWHC 2365 (TCC), HHJ Toulmin QC
stated that the adjudicators power to take the initiative in
ascertaining the facts and the law (s.108(2)(f) HGCRA) extended to
orders relating to disclosure.
37. Accordingly, it would appear to be a matter for the
individual adjudicator, constrained by the principles of natural
justice, as to which documents he requires to be disclosed.
38. Where a party makes an application for disclosure, the
adjudicator is entitled to refuse the application if the size and
nature of the request is inappropriate given the size and nature of
the dispute, particularly if the purpose of the application is
predominantly tactical (see CIB v Birse (supra at 196)).
39. It is not clear what powers the adjudicator has in the
event that disclosure is resisted. The proper response is
probably for the adjudicator to simply draw an adverse
inference. This was the view taken by the adjudicator in
CIB v Birse (supra at para 129)
which appears to have been supported by HHJ Toulmin QC.
The articles and papers published by Keating Chambers are for the purpose of raising general awareness of issues and stimulating discussion. The contents must not be relied upon or applied in any given situation. There is no substitute for taking appropriate professional advice. © All rights reserved.
Back to Seminars