printer friendly versionPrint this Page

Procurement Law

Tenderers dissatisfied with the tendering process want to know whether they have a claim against the party who awarded the contract.  Those who commission works in the private and public/utilities sectors will increasingly need assistance in scrutinising their own conduct as they face actions for damages and injunctions in respect of their treatment of tenderers.

Keating Chambers’ involvement with procurement is not limited to representation of litigants in headline decisions in the courts.  Its members routinely advise at early stages of projects when the aim is to avoid the kind of irregularities exposed in the Harmon case (see below).  Members of Keating Chambers advice is especially sought by project sponsors, lenders and contracting authorities and their consultants, all of whom wish to ensure compliance with the regulatory regime.

Conversely, contractors may wish to protect their position pending the outcome of the tendering process if they are concerned about the procedures being followed.  When the outcome is known, both unsuccessful and even successful tenderers need to understand the extent to which it is final or likely to be susceptible to challenge, while the client/commissioning institution may have to prepare to meet potential claims.  Time limits for valid challenges to award decisions are extremely tight. Keating Chambers have specialist procurement law barristers at all levels of seniority to ensure that timely advice is available in all these situations, with advocacy and dispute resolution services on call should the case demand them.

Many procurement matters previously handled by members of Keating Chambers have related to matters from a wider scope than just construction and engineering projects. These projects have included the procurement of goods and services such as computers, food, photocopiers, books, stationery, energy, cleaning, travel and maintenance. 

KEATING CHAMBERS AT THE FOREFRONT OF THE DEVELOPMENT OF PROCUREMENT LAW
OBTAINING ADVICE AND OTHER ASSISTANCE

The case of Harmon CFEM Facades (UK) Ltd v The Corporation Officer of the House of Commons (ConLR Volume 67) is one of the most important decisions ever made by an English Court on the impact of European procurement law on the construction industry of this country.  It concerned a very high-profile project, Portcullis House, the addition to Parliamentary accommodation at Westminster.  The curtain walling/fenestration contract was won by a British firm, although Harmon, the British subsidiary of a French company, had submitted the lowest tender.  Harmon felt aggrieved by the way in which the tendering process was carried out by the Parliamentary Works Directorate (PWD) and challenged the legality of the award.

His Honour Judge Humphrey Lloyd QC held that the PWD had ‘deviated from the Public Works Regulations procedures’ in having ‘flirted’ with one particular tenderer and that the expressions ‘overall value for money’ and ‘most economically advantageous’ were too nebulous to be valid criteria for declining to award on the basis of price.

Harmon were, in the end, successful in their action to obtain substantial damages from the House of Commons.  Harmon were represented by counsel from Keating Chambers in this landmark case in modern procurement law.

Richard Fernyhough QC acted on behalf of Harman

In the case of BSF Group Ltd v (1) Secretary of State for Defence (2) Purple Foodservice Ltd  [2006] EWHC 1513 (Ch), BSF, who trade as 3663, sought an injunction to prevent the Ministry of Defence from awarding the contract for the supply of food to UK troops worldwide to Purple Foodservice Ltd. 3663 were the existing contractor and had tendered for the new contract. They argued that the Ministry of Defence had wrongfully deprived them of the opportunity to enter into a negotiated phase of the tender and, ultimately, that they should have been awarded the contract. 3663’s application for an injunction was refused. The Chancery Division Judge did not accept that 3663 had a right to enter into a negotiated phase.

The case involved consideration by a Court for the first time of precisely what is required if an employer seeks tenders using the negotiated procedure. The Secretary of State for Defence was represented by leading and junior counsel from Keating Chambers.

Paul Darling QC and Sarah Hannaford QC acted for the Secretary of State on this case


THE IMPACT OF PROCUREMENT LAW

Procurement law is of increasing importance to the construction and technology industries.  Throughout the 1990s, EU procurement directives were implemented in the UK by subsidiary legislation such as the Public Works Contracts Regulations, and Public Supply Contracts Regulations and the Utilities Contracts Regulations.  The effect was to bring most major public works, services and supplies contracts, in addition to utilities contracts (including water, energy and transport), within the regulatory regime of EU procurement law.  As from 31 January 2006, based on new EU directives, the regulatory regime in the U.K. was consolidated and updated. On that date, the new Public Contracts Regulations 2006 and Utilities Regulations 2006 came into force, in relation to contract award procedures commenced on or after that date.

Contracts let in ways which breach specific procedural rules or the general principles of transparency and equality can be the subject of judicial challenge.  Dissatisfied unsuccessful tenderers have the opportunity to challenge proposed contract awards either by way of injunctions or by claiming damages. In the light of the ECJ decision in the Alcatel case, a standstill period of 10 days has been introduced into the UK Regulations in order to allow an aggrieved tenderer a 10 day period, after notification of the proposed contract award, to ask for further information about the award decision and, if appropriate, to challenge the decision in Court, before the contracting authority may finally award the contract. An injunction could prevent the contract being awarded to the successful tenderer and involve the employer in huge expenditure and delay, especially if it is required to re-tender from scratch. Damages claims can also be very substantial: tenderers often claim, not only their wasted tender costs, but also loss of profit over the course of the contract.

A number of significant practical consequences flow from these developments.  Public authorities and utilities frequently need advice on their procurement procedures, in order to prevent breach of the regulations and also if the legality of a contract award is challenged by a disappointed tenderer.  Similarly, contractors will often wish to obtain advice if they believe their position has been prejudiced by the way in which the tender was handled.


Further Information
For further information on how our members can assist you, please contact the Senior Clerks, John Munton and Nick Child, in the first instance, on +44(0)20 7544 2600. They and their teams of Clerks will be pleased to advise you on the member of Keating Chambers appropriate to your requirements.